Hampden Road Sewer Upgrade

Hampden Road Sewer Upgrade

Category Completed Infrastructure Projects
Project Start Date 11/11/2013
Expected Completion Date 31/12/2013
Proponent District Council of Mount Barker
Project Status Complete
Contact Work: 08 8391 7290
Email: council@dcmtbarker.sa.gov.au

As a part of the Asset Renewal Program, the District Council of Mount Barker will be upgrading a portion of the main sewer pipe network at the end of Hampden Road, Mount Barker, near the Steam Ranger Railway corridor. The upgrade will cater for increasing daily flows and periods of high flows such as those experienced during the wetter months.

Council has undertaken planning for the upgrading of the eastern end of Hampden Road and it is essential that this sewer upgrade work is completed prior to the street upgrading works.

 

2 December 2013

CAMCO have advised that the upgrade works will now commence on Tuesday 3 December 2013 and remain scheduled to be complete prior to Christmas.

Hampden Road Sewer Upgrade - Notice to Residents December 2013(46 kb)

 

 

28 October 2013

Council’s contractor, CAMCO, will commence construction in late November 2013.  It is expected that the sewer works will be completed by end of December 2013.  The road upgrade will follow in the first half of 2014. 

The work will mostly be carried out between the hours of 7.30 am and 6.30 pm, with some night works also required. There will be occasions where the end of Hampden Road will be closed to facilitate works and to ensure the safety of the public and contractors.  Access to properties will be maintained throughout the project, however there maybe times where this is not possible and the occupants of affected properties will be consulted prior to any access restricting activities.

Council apologises for any inconvenience that the work may cause and will endeavour to meet any special access needs properties or businesses may have.  

Council’s Contract Supervisor, Mr Ian Powell, can be contact on mobile 0408 970 966 for any out of hours matters in relation to this project.