Sewage Pipeline

Sewage Pipeline

Category Completed Infrastructure Projects
Project Start Date 01/10/2015
Expected Completion Date 30/06/2016
Proponent District Council of Mount Barker
Project Status Complete

Temporary Traffic Restrictions for Sewage Pipeline Construction

Alano Utilities (Mount Barker) Pty Ltd is constructing a 12 km long sewage pipeline to take sewage from the Aston Hills residential estate in Mount Barker to a Waste Water Treatment Plant (WWTP) under construction near Kanmantoo.

 

March 2016

Back Callington Road will temporarily be closed to traffic between Cattle Route and Summit Road commencing 3 March 2016.  The works are expected to be complete by 1 April.

The road will be reopened to traffic when workers are off site.

Please contact the contractor's Project Manager, Joshua Magor, on telephone 0426 270 981 if there are any queries as works progress or Alano Water on telephone 8240 2733 or email Admin@alanowater.com.

 

February 2016

Excavation works will be underway commencing February 2016 to end of June 2016.  Please note these periods are approximate depending on terrain and there may be some traffic delays.

  • Back Callington Road
  • Springs Road

Please contact the contractor's Project Manager, Joshua Magor, on telephone 0882 402 733 if there are any queries as works progress.

 

December 2015 Key Dates

Hair Road / Old Princes Highway Crossing 14 Dec
Proctor Road 15 Dec
Renfrey Road 16, 17 Dec
Bartholomew Road 18 Dec
Extension of Bartholomew Road (un-made) 21 Dec
Flood Mitigation Easement 22 Dec