North Terrace Littlehampton Footpath

North Terrace Littlehampton Footpath

Category Completed Infrastructure Projects
Project Start Date 09/11/2015
Expected Completion Date 18/12/2015
Proponent District Council of Mount Barker
Project Status Complete
Contact Person Infrastructure and projects
Contact Work: 08 8391 7290
Email: council@dcmtbarker.sa.gov.au

The 2015/16 Mount Barker District Council Footpath Replacement Program includes the installation of a paved footpath, using Littlehampton Clay Brick Pavers, along the northern side of North Terrace, Littlehampton, from the Railway Line at Willow Park to Cleggett Road.

The alignment and width will follow the current asphalt path. Driveway cross overs from the kerb to the property boundary will be paved except where they are currently constructed of brick paving or concrete in good condition.  Trees and shrubs will be trimmed to property boundaries.

The contractor is scheduled to commence the week of 9 November 2015 and be complete by December, subject to favourable weather and no unforeseen circumstances. Work will commence at the Railway Line and move progressively to Cleggett Road. 

There will be some inconvenience regarding access whilst footpath and driveway construction is being carried out.  All endeavours will be taken to keep the disruption to residents and properties at a minimum.