Martin Road & Barker Road Junction Upgrade

Martin Road & Barker Road Junction Upgrade

Category Completed Infrastructure Projects
Project Start Date 01/06/2015
Expected Completion Date 31/07/2015
Proponent District Council of Mount Barker
Project Status Complete
Contact Person Infrastructure and Projects
Contact Work: 08 8391 7290
Email: council@dcmtbarker.sa.gov.au

As part of the Springlake development, the developer is required to upgrade the junction of Martin Road and Barker Road, Mount Barker.

September 2015

Construction works have been completed and the roads reopened.

August 2015

Work has been recommenced with the road scheduled to reopen during the week of 24 August.

July 2015

Progress has been delayed due to wet weather.  It is now expected that the road will be reopened by the end of August.

June 2015

Works will include installing sewer, water and CST services along Barker Road, and upgrading Barker Rd itself from Martin Rd to the Connector Rd.

To safely complete these works, the junction will be fully closed to all vehicles.  It is expected that construction will commence the week of 8 June and be complete by July 2015.

An alternative route is via Barker Rd and Native Ave onto Flaxley Road.  Motorists are advised that these roads are unsealed and to drive to the conditions.

 