Kanmantoo Stormwater Upgrade

Kanmantoo Stormwater Upgrade

Category Completed Infrastructure Projects
Project Start Date 25/05/2015
Expected Completion Date 16/10/2015
Proponent District Council of Mount Barker
Project Status Complete
Contact Person Infrastructure and Projects
Contact Work: 08 8391 7290
Email: council@dcmtbarker.sa.gov.au

The District Council of Mount Barker is committed to maintaining stormwater infrastructure to minimise where possible the impacts of stormwater and potential for flooding.

A minor stormwater capital works program has been developed to assist in prioritising and scheduling works throughout the district.

Kent Road

Council has appointed a contractor to undertake an upgrade of the stormwater  infrastructure to improve capacity and flows at Kent Road, Kanmantoo. 

The scope of work will include swale shaping along Renfrey Road (between Bartholmew Rd and Kent Rd), underground pits and pipes along Kent Rd and across Young Rd (to the channel in unmade Kent Rd road reserve), pavement works and kerb at the intersection of Young Rd and Kent Rd.

The contractor has indicated commencement the week of 17 August 2015 and completion by October, subject to weather and any unforseen issues.

 

Cook Street 

May - June 2015

Council has appointed a contractor to undertake an upgrade of the stormwater  infrastructure to improve capacity and flows at Cook Street, Kanmantoo. 

The scope of works will include construction of new stormwater lines, headwalls and stormwater pit, together with associated earthworks.

The contractor will commence in the week beginning 25 May 2015 and is expected to be complete by end of June, subject to weather and any unforseen issues.