Oborn Road, Mount Barker Stormwater Works

Oborn Road, Mount Barker Stormwater Works

Category Completed Infrastructure Projects
Project Start Date 02/06/2014
Expected Completion Date 30/06/2014
Proponent District Council of Mount Barker
Project Status Complete
Contact Person Infrastructure and Projects
Contact Work: 08 8391 7290
Email: council@dcmtbarker.sa.gov.au

The upgrade will improve the inlet capacity of the existing underground stormwater infrastructure.

Works will include the removal of an existing stormwater pit and replacing it with a double pit, the installation of new stormwater pipe and also the installation of an additional double stormwater pit, together with associated earthworks.

Access to Oborn Road and properties will be maintained at all time.  Traffic management will be implemented to minimise disruptions during the works.

The contractor will commence in the week beginning 2 June 2014 and works will be undertaken between 7am to 5pm Monday to Friday. It is expected that works will be completed within 2 weeks from commencement subject to weather and any unforseen issues.

Should you require any further information or have any queries as works progress:

  • Civil Works Project Manager, Simon Bowring, NEO Infrastructure, Mob 0409 119 397
  • Council’s Assistant Project Manager, Megan Bonehilll,  Mob 0400 301 448

 

6 Dutton Road, Mount Barker SA 5251
T 8391 7200