Road Resurfacing 2014/15

Road Resurfacing 2014/15

Category Completed Infrastructure Projects
Project Start Date 01/07/2014
Expected Completion Date 30/06/2015
Proponent District Council of Mount Barker
Project Status Complete
Contact Person Chris Massey
Contact Work: 08 8391 7290
Email: council@dcmtbarker.sa.gov.au

Council undertakes a program of road resurfacing throughout the district each year. The list of roads will be updated as the program progresses.

The District Council of Mount Barker is committed to maintaining roads in good condition to provide a safe environment.  Over the financial year, a number of streets and roads are scheduled to be resurfaced.  Please refer below.

Marks will be painted on the road indicating start and finishing points.  Some roads will also have concrete works completed including replacement of kerb and gutter, driveway crossings and spoon drains.

The work will necessitate closing sections of the road for a period of time on the day that construction is undertaken.  During this time there may be limited access to driveway entrances and vehicles should not be left parked on the road.

All endeavours will be made to ensure a minimum of inconvenience, but alternative routes should be planned while these works are underway.

May - June 2015

Township Street Location Type
Nairne Easter Street In front of No. 3   Kerb and gutter
    In front of No. 4  Kerb and gutter
    In front of No. 4   Driveway
    In front of No. 5  Kerb and gutter
    In front of No. 6  Kerb and gutter
    At intersection with Britannia St on West side  Kerb and gutter
  Gladstone Street Eastern End in front of No. 24 a Mountable Kerb
    Western End opposite No. 24a Mountable Kerb
    Western End in front of No. 24a  Mountable Kerb
  Military Rd                     005 - Nairne Rd to Pine Ridge Rd   Asphalt patching
Hahndorf Balhannah Road  North side - Entrance to Motel across from church  Driveway
    North Side near culvert  Kerb and gutter
    North side - In front of school  Driveway
    South side - entrance to school Driveway
    South side  Kerb and gutter
  Kavel Drive Intersection with English Street Kerb and gutter
  Thiele Grove Between No. 7 and 11 Kerb, gutter and driveway
Echunga 27 Marianna Road   Kerb, gutter and driveway
  Darby Rd                      Echunga Rd and Darby La                                     Asphalt patching
Meadows Kondoparinga Road Intersection with Brown St  Spoon drain
    Immediately south of Intersection with Brown St Kerb and gutter
    No. 12  Kerb and gutter
    No. 14  Kerb and gutter
    No. 16 Kerb and gutter
  Razor Back Road Battunga Rd to 1 KM West   Asphalt patching
  Morris Rd                      Brookman Rd and Rowley Rd                                    Asphalt patching
       
Mount Barker Skipper Street Intersection with Weld Court, South side Kerb and gutter
 

Hutchinson Street 

No. 47 Kerb, gutter and driveway
 

Mann Street 

In front of Church in Mann St  Crossing, kerb and gutter
    Around corner into Hutchison Street Crossing
    Opposite side of road from church Kerb and gutter
    In front of No. 9  Spoon drain
    In front of CWA building  Kerb and gutter
    Side of Salvation Army Building in front of tree  Kerb, gutter and driveway
  Waterford Avenue Intersection with Claret Ash Drive Kerbing
Green HillsRange                  Greenhills-flaxley Rd                Quarry Rd and end road seal  Asphalt patching
Harrogate                Harrogate Road Cockatoo Rge to Church Road Asphalt patching
Dawesley                      Harrogate Rd                    Old Princes to 1 km North  Asphalt patching

 

Night Works 23 - 27 February 

Road

 

Section

Work Type

Indicated Date for Work

Cameron Road

From Pedestrian Crossing to car park entrance

Kerb and Guttering

23 February

Cameron Road

From Pedestrian Crossing to Gawler Street

Resurfacing

26 & 27 February

 

Hutchinson Street

Portion south of Mann St Roundabout

Resurfacing

26 & 27 February

 

MacFarlane Terrace

From Roundabout to rear of Homemaker Centre

Resurfacing

26 & 27 February

 

The work will be undertaken at night and will result in additional noise.  The EPA has indicated Public Infrastructure work can be undertaken at this time as long as the contractor complies with environmental criteria and minimises any nuisance.

The work may necessitate closing sections of the road for a period of time on the nights that construction is undertaken.  During this time there may be limited access to driveway entrances and vehicles should not be left parked on the road.

 

Kanmantoo, Proctor Road

A sort section of Proctor Road, Kanmantoo, between Nursery Road and the 50 km/hr speed sign, will be reconstructed and a bitumen spray seal applied.

This work is scheduled for 17 to 20 February 2015. Please note these dates may vary due to unplanned external influences such as unsuitable weather conditions.

The road will be open during the work other than when the spray seal is being laid, at which time it will be closed for approximately 15 minutes.

 

Paddy Hill Road, Mount Barker 

Click here for more information.

 

January/February 2015

Notice from Council’s contractor advising the actual date of work will be provided to property owners 1 to 3 days prior to commencement.

Road

 

Section

Work Type

Indicated Date for Work

Duffield Ave, Mount Barker

Wellington Rd to Murray Av

Resurfacing

28 January – 30 January

Edinborough St, Nairne

Between Jeffrey St and Bartley St          

Concrete work

27 – 6 February

Edinborough St, Nairne

Jeffrey St to Bartley St

Resurfacing

16 February – 20 February

Farquharson St, Nairne

Low point in road and  near Intersection with Main Rd 

Concrete work

20 – 30 January

Farquharson St, Nairne

Nixon St to Main Rd

Resurfacing

16 February – 20 February

Murray Ave, Mount Barker

Sims Rd to Acacia St

Resurfacing

28 January – 30 January

Preiss Cl, Nairne

In front of No. 9

Concrete work

20 – 30 January

Preiss Cl, Nairne

Full length

Resurfacing

16 February – 20 February

Pulleine Rd, Nairne

At intersection with Elm Cr

Concrete work

20 – 30 January

Pulleine Rd, Nairne  

88m west of Elm Ct to Nairne Rd   

Resurfacing

16 February – 20 February

Please note:  Commencement and completion dates may vary due to unplanned external influences such as weather conditions.

 

Resealing - Echunga

12 November 2014 - Road resurfacing works within Mount Barker will commence from 20 October 2014 and be concluded by 24 October at the following locations

Location

Extent of Works

Scheduled Date of Works

Scottsburn Road

Full Length

17 November

Hawthorn Road

Between Liebelt Summer Track and Ironstone Road

18 November

Diggings Road

From Todd Road to 1 km South

19 November

Berry Road

From Shepard Road to 1.3 KM West

20 November

Bower Road

From Rowley Road to just past bend at winery entrance gate

21 November

Griggs Ave

From Harvey Rod to end of seal

21 November

 

Resealing - Littlehampton

6 November 2014 - Road resurfacing works within Littlehampton Township will commence from 7 November 2014 and be concluded by 14 November at the following locations:

  • Gum Tree Drive - from Benjamin Gray Drive to Saint James Drive
  • Monk Avenue - Rushton Court to end

 

Road Patching Works

Stamps Road

17 October 2014  - The full length of Stamps Road will have road patching works undertaken between the hours of 9.00am and 4.00pm from 20th to 22nd October 2014. The road will be temporarily closed to through traffic at times during these periods. Council's contractor will have traffic management measures in place.

 

Resealing - Mt Barker

17 October 2014 - Road resurfacing works within Mount Barker will commence from 20 October 2014 and be concluded by 24 October at the following locations:

  • Howard Lane - from Alexandrina Road to Wellington Road
  • Jubilee Crescent - Maldon Street to Daw Avenue
  • Princes Road - Hughes Street to Edward Street

11 September 2014 - Road resurfacing works within Mount Barker will commence from 15 September and be concluded by 19 September at the following locations:

  • Power Court - Full Length
  • Hanna Avenue - Full Length
  • Barratt Avenue - Full Length

 

Resealing - Nairne

9 September 2014 - Road resurfacing works within Nairne Township will commence from 15 September and be concluded by 19 September at the following locations:

  • Elizabeth Streeet - North Railway Terrace to Packard Street
  • Plowman Close - Full Length
  • Stockham Street - Full Length
  • West Terrace - Full Length

 

Resealing - Mt Barker

20 August 2014 - Resealing will shortly commence for the following roads:

Poplar Cr – Hawthorn Wy to Victoria Rd

22 to 29 August

Bruce Cl – Zanker Dr to End

25 to 29 August

Sheidow Cr – Zanker Dr to End

Stonybrook Gr – Donoghue Rd to End

Ray Orr Dr – Wade St to Cook Ct

26 August  to 2 September

Bowden Ct - Ray Orr Dr to No. 5 Bowden Ct

Cook Ct – Ray Orr Dr to End

Pridmore Tce – Adelaide Rd to Hutchinson St

27 August to 4 September

McLaren St – Druids Av Dunn Rd to

Cameron Rd – Dunn Rd to Gollan Cct

Cameron Rd – No 31 Cameron Rd to Paddy Hill Rd

 

Resealing - Mt Barker

10 July 2014 - Preparations for resealing will commence on Friday 11 July for Princes Road (Albert to Charles) and Ruben Pope Court with resurfacing works to follow early next week subject to weather.

 

Previous Year's Works

Roads resealed in previous years can be found on the Road Resealing 2013/14 page.

 

 