Unsealed Roads Program 2017/18

Unsealed Roads Program 2017/18

Category Infrastructure Works Programs
Project Start Date 01/06/2017
Expected Completion Date 30/06/2018
Proponent District Council of Mount Barker
Project Status Current
Contact Person Field Services Unit
Contact Work: 08 8393 6450
Email: council@mountbarker.sa.gov.au

Council undertakes an Unsealed Roads Program throughout the district each year. The list of roads will be updated as the program progresses.

The Mount Barker District Council is committed to maintaining roads in good condition to provide a safe environment.  Over the financial year, a number of unsealed roads are scheduled for patrol grading or resheeting. 

During works there may be limited access to driveway entrances and vehicles should not be left parked on the road.

All endeavours will be made to ensure a minimum of inconvenience, but alternative routes should be planned while these works are underway.  Road users are requested to adhere to any detours that will be in place.

Roads are maintained by zones as outlined below.

 Patrol Grading Zones

 

Unsealed Renewal Program

 January 2018 - March 2018

Council will be undertaking road works on the following sections of road between January and March 2018, weather permitting.

 

Road

Section

Township

Archer Hill Road

Long Valley Road to 1756m east Long Valley Road

Bugle Ranges/ Highland Valley

Phillips Hill Road

Spring Gully Road to Bull Creek Road

Bull Creek

Boomerang Road

Ellis Road to 433m east Ellis Road

Meadows

Bassham Road

1058m east Pocock Rd to Sand Rd

Jupiter Creek

Rowe Road

Long Gully Road to Berry Rd

Juipiter Creek

Todd Rd

Feder Rd to Long Gully Rd

Chapel Hill

Sandow Road

Onkaparinga Valley Rd to 1024m south Onkaparinga Valley Rd

Verdun

Snelling Road

2127m west Echunga Rd to Lubasch Rd

Hahndorf

 

Sealing Unsealed Roads 

Council has no formal plans to seal unsealed roads or construct new unsealed roads at this point in time however, it is in the process of investigating an upgrade program for unsealed roads that will be subject to funding.

 

Dust Suppression

Dust suppression treatment involves the laying of profiling material and then a spray seal of emoleum.  Whilst this may give the appearance of bitumen, it is only a temporary dust suppression measure (lasting up to 5 years) and not a bitumen finish.  The road remains classed as an unsealed road.

Unfortunately, road profiling materials are no longer available and Council has discontinued the dust supression program.

Council is exploring alternative treatment options and will continue to grade unsealed roads in the meantime.

 

 

 

 